- Sektör: Government
- Number of terms: 5883
- Number of blossaries: 0
- Company Profile:
A condition or capability that must be met or possessed by a system, product, service, result, or component to satisfy a contract, standard, specification, or other formally imposed documents. Requirements include the quantified and documented needs, wants, and expectations of the sponsor, customer, and other stakeholders.
Industry:Business services
A modification of a logical relationship that directs a delay in the successor activity. For example, in a finish-to-start dependency with a ten-day lag, the successor activity cannot start until ten days after the predecessor activity has finished. See also lead.
Industry:Business services
A provision in the project management plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g., management reserve, contingency reserve) to provide further detail on what types of risk are meant to be mitigated. The specific meaning of the modified term varies by application area.
Industry:Business services
A systematic way of reaching an intended outcome. Philosophically, change is what project management is all about.
Industry:Business services
A modification of a logical relationship that allows an acceleration of the successor activity. For example, in a finish-to-start dependency with a ten-day lead, the successor activity can start ten days before the predecessor activity has finished. See also lag. A negative lead is equivalent to a positive lag.
Industry:Business services
A comprehensive, realistic, and deliverable plan to accomplish the team mission and deliver the project. It includes Initiate & Align and Plan the Work elements, including a schedule and a budget.
Industry:Business services
A dependency between two project schedule activities, or between a project schedule activity and a schedule milestone. See also precedence relationship. The four possible types of logical relationships are: Finish-to-Start; Finish-to-Finish; Start-to-Start; and Start-to-Finish. The finish-to-start relationship is the most common type of logical relationship and is the default in most scheduling software.
Industry:Business services
The process of tracking team member performance, providing feedback, resolving issues, and coordinating changes to enhance project performance.
Industry:Business services
The process of managing communications to satisfy the requirements of, and resolve issues with, project stakeholders.
Industry:Business services